Traffic Update for the week of 11/14/11
Here is the traffic and construction update for the week of 11/14/11:
Main Street:
Paving has been completed on Main Street between George Street and Noble Street as of Saturday. Lynch Construction will now focus on the following:
Monday – The side streets off of Broad Street and Main Street will be paved leading into the newly paved main roadways. These feeder streets could be closed up to 2 hours each as they lay the pavement and it sets.
The rest of the week – The paving crews will be working on the driveway aprons of both the commercial and residential properties on Broad Street, East Silver Street, West Silver Street and Main Street.
Lynch should also be able to complete the lane markings by mid week.
Construction is expected to run into the first week of December, weather permitting, with the final pieces put into place in early March.
Park Square Area:
The work on the Park continues and it is starting to become very noticeable as you drive by. Many of the concrete foundation pieces are in place as are some of the lighting pieces.
The addition of granite pieces have also started. You are also seeing some of the safety bollards being installed around the outside portion of the park.
It is starting its return to be the focal point of our southern reach of downtown. Spring will result in our Park coming to life and we will be able to enjoy the new area during the summer.
Broad Street/East Silver Street/West Silver Street:
Monday – The side streets off of Broad Street and Main Street will be paved leading into the newly paved main roadways. These feeder streets could be closed up to 2 hours each as they lay the pavement and it sets.
The rest of the week – The paving crews will be working on the driveway aprons of both the commercial and residential properties on Broad Street, East Silver Street, West Silver Street and Main Street.
Lynch should also be able to complete the lane markings by mid week.
Construction is expected to run into the first week of December, weather permitting, with the final pieces put into place in early March.
Thomas Street Lot:
The Thomas Street public parking lot has been paved and is ready for regular use. Thank you for your patience during this phase of improving our downtown.
Westfield G&E Work Zones in various sections of the City:
No schedule of work was provided.
Great River Bridge Project:
The contractor laying pavement on the bridge deck. They are continuing on a plan to begin traffic flow going southbound on the renovated bridge during Thanksgiving week – weather permitting.
As a reminder this is a State funded/State controlled project and we are gathering information and moving it out to you as it becomes available.
Other info:
Please remain alert and follow the directions of the Westfield Police Officers who will be working throughout the work sites.
Please remember to use your directional signals so we all know your intentions and be alert for the police personnel who will be guiding you through the construction zones.
As the Holiday season fast approaches please remember to support our local businesses – they are our neighbors and friends.
Thank you for your patience as we make Westfield a better place to live, work and relax.
The Westfield Business Improvement District would like to thank Capt. Michael McCabe and the Westfield Police Department and City Councilor Jim Brown for making this information available to all of us so we may plan accordingly.